Place First, Salford
Braithwaite Group were appointed by Place First to carry out their new HQ in Salford. The space has different amenities including a reception area, break out areas, coffee section, meeting rooms, reading areas and temporary workspace.
During the project, the Place First team decided they had to make a statement with this space, Braithwaite Group worked closely with our in house design team and building team to deliver this project, which changed drastically from the initial tender stage, which showed with the incredible end results.
Whilst working on site, Braithwaite Group re-priced the new design and delivered the project with only a 1 week extension on the initial 8 week programme.
The works carried out were the following:
- Full strip out to exposed original features
- Installation of structural steel to create openings
- Installation of new suspended raft
- Manufacturer and installation of new timber partitions
- Installation of new kitchen
- Installation of new stone worktops
- Manufacture and installation of bespoke joinery
- Installation of new metal work features
- Installation of raised access floor
- New mechanical air cooling system installed
- New electrics throughout
- New decoration throughout
- New tiling to floors
- New entrance matting
- New carpets
- Alterations to all windows
- Spraying to all windows
- Installation of all furniture
The project was received with huge delight from Bruntwood and their customers.